February 2019 Bond Update

Wa-Hi
• Jackson Construction of Walla Walla named General Contractor
• Perfection Glass of Walla Walla to install window configuration mock-ups in Principal Higgins’ office for stakeholder feedback
• Architects West begins conceptual design of new science building. Construction begins next fall

Pioneer MS
• Site survey work has begun
• Pioneer staff to tour regional schools in March

Lincoln HS
• Site survey work has begun

Berney
• Project team and facilities staff analyzed four options for HVAC replacement. Bidding will take place this spring with construction beginning in June

Blue Ridge
• Roof consultant and facilities staff performed targeted excavation of soil on roof to determine condition of roofing membrane and detailing